Larsen piling, U200 piling, and C200 piling are all effective methods of foundation reinforcement that are constructed in many projects. Especially, larsen piles are built in massive, large-volume projects and there are many methods of construction, including pressing larsen piles with vibrating hammers.

The method of pressing larsen piles by vibrating hammer is quite popular. Construction of larsen piling by vibrating hammer has the following technical characteristics:

- Creates a vibration force transmitted to the pile head

- Continuously transmits down the pile head with frequency oscillations with a specified amplitude and direction

- Fast and accurate construction time while limiting noise pollution

Advantages of construction of larsen piles by vibrating hammer:

- Save construction time because construction is fast and relatively accurate

- Works with limited space can be used

- Reasonable price, not too expensive

- Convenient in terms of transportation

Its disadvantage is that it is not suitable for narrow space works

The pressing process is as follows:

The first of course will be the preparation of machinery, equipment, construction materials: Piles, vibrating hammers, pile presses...

Determine the location of the piles while constructing the bracing systems. To determine the location of pile driving, the construction units will rely on the design. In fact, many buildings may not implement bracing systems, however, depending on the type of construction work.

Pile:

- Use a vibrating hammer to clamp the pole as firmly as possible to ensure safety during construction.

- Proceed to raise the pile to the vertical position

- Next, the poles must be adjusted to the specified position, the deviation must be within the allowable range